Some updates from the construction manager:
If you're still having trouble finding parking, one resource to investigate is School Pool, a free public service that coordinates carpooling to school: https://www.schoolpool.511.org
- The crew is continuing work on the new building foundations.
- Large equipment compacting the soils is on site.
- More excavation will be happening soon to install the building footings.
- The fence configuration will stay as is until the end of the calendar year.
- New orange lines have been painted across the yard and the basketball hoops were relocated to a more suitable location.
- Bike racks have been relocated to the underside of the metal stairs.
- It's been pretty loud at times and the good news is that during testing days, no noise will be allowed during testing hours.
- Noise limits are also observed during school hours. The contractor tries to make the most noise before classes start and after they’re done.