The crew has been hard at work over Spring Break and the changes are dramatic. The update from the project manager for next week is:
Some pictures from Thursday, April 3:
- Bungalows 107 and 108 have been removed and two brand new ones are now in place, between the play structure and bungalow 112. Mr. Flanagan and Ms. Visalli will now enjoy leak-free, heated and cooled, newly carpeted classrooms.
- The construction fence has been removed from around the new bungalows.
- A new construction fence has been erected to separate the jobsite from the school yard. This new arrangement of reduced yard space will potentially stay through the end of December 2014/early January 2015.
- The new building construction is well underway, with foundation and excavation work going on.
- Concrete trucks and pumps will be here soon (possibly the week of 4/14, depending on weather and progress).